Producer wells being drilled from East Azeri and Deepwater Guneshli platforms


Baku, May 19 (AzerTAc). During the first quarter of 2011, from the East Azeri platform, BP-Azerbaijan completed drilling activities on D-19 producer well which was started in September 2010. It currently have ongoing drilling on another oil producer well – D20 which is planned to be delivered in the fourth quarter of 2011.
On Deep Water Gunashli platform, the company is currently drilling the E15z oil producer which is planned to be delivered in the second quarter of 2011. The next well –E16 is planned to be completed by the first quarter of 2012.